The construction of a 1 megawatt (MW) hydroelectric facility at the Upper Collinsville Dam on the Farmington River in Canton resumed construction after the closing of the construction loans. The project is the result of significant expertise and innovation from many stakeholders, including the Town of Canton, The Provident Bank, the Department of Energy and Environmental Protection (DEEP), and the Connecticut Green Bank. Once operational, the facility is projected to generate an average 4.3 million kWh of clean energy and save 3.2 metric tons of CO2 emissions annually, while preserving a historic powerhouse, enhancing public safety features, and revitalizing aquatic habitat by allowing fish to swim upstream for spawning for the first time since 1867.
The dam is owned by the State of Connecticut and the water rights will be leased to Canton Hydro over a 30-year period. Utilizing the state’s Virtual Net Metering program, State of Connecticut owned buildings through DEEP will benefit from the lower cost renewable energy.
The final requirement for the project was securing financing, which was accomplished through a creative partnership structure. The total project cost is approximately $6.6 million with the Green Bank providing a $1.2 million subordinate loan and $500,000 limited guaranty to leverage an approximately $4.7 million senior loan from The Provident Bank through the U.S. Small Business Administration (SBA) 504 Loan program. Additional equity is being provided by Canton Hydro.